9.3.15

"The Monthly Face-2-Face" - # March 2015


"MEASURING THE PHYSICAL PROGRESS " 
After realizing the initial schedule, accepted and approved by #stakeholders, there is the equally difficult task of updating it and making it live. The basic input data of the #schedule are the actual start and end dates for completed activities, progress and estimated end dates for current activities.
If the accuracy of the recorded dates depends mainly on the rigor of the planner in the updates, the percentage of completion it, is much more complex to understand.It is indeed necessary to decide what kind of progress is the best indicated dependent on the nature of the project, the type of task to update, the level of detail of the planning.